Week - 1 |
Removal-installation of ADI and performing BITE test. |
Week - 2 |
Removal-installation of HSI and performing BITE test. |
Week - 3 |
Removal-installation of VSI and performing BITE test. |
Week - 4 |
Removal-installation of DME Antenna |
Week - 5 |
Removal-installation of ATC Antenna |
Week - 6 |
Removal-installation of RA Antenna |
Week - 7 |
Removal-installation of VHF navigation (VOR) system components (LRUs) |
Week - 8 |
Test of VHF navigation (VOR) system components (LRUs) |
Week - 9 |
Removal-installation of weather radar system components |
Week - 10 |
Functional test of weather radar system components |
Week - 11 |
Performing generator power control/voltage adjustments. |
Week - 12 |
Removal-installation of emergency battery. |
Week - 13 |
Removal installation of electrical distribution systems' components (contactor, relay, RCCB etc.). |
Week - 14 |
Removal-installation of APU and Main batteries. |